Design Team Meeting Minutes

Spring 2009 Minutes

April 3, 2009

Accomplishments
  • Held a meeting with Monroe and the people in Honduras. It was a basic Q&A session and helped clear up a lot of things so we can proceed. (notes can be found on the Tasks page linked at the bottom)
Metrics
Outcomes
  • Decided that ports between channels will be located at the top of the wall instead of the bottom
  • Sludge drain dimensions will be constrained so that they must be able to cover a 3-4" pipe
Issues
  • Chemical stock tanks need to be changed so that a volume and dimensions are given. This will give engineers the option of using barrels or building tanks.
  • In order to determine baffle thickness the baffle area needs to be included

Any Overall Team Comments:

Continued division of tasks can be found here