Our main goal is to Successfully aid in the construction and completion of the Marcala Water Treatment Plant.

By Feb 15th we hope to finish the Marcala detail including:

  1. Determine Baffle Spacing for Section A of flocculator.
  2. Specify Plant Leveling Tank Mechanics
  3. Calculate Number and Size of Orifices in Effluent Launder from Sedimentation Tanks to Plant Leveling Tank

Once the final aspects of the Marcala Water Treatment Plant are designed, we will work to integrate our designs with the automated design team.

For the remainder of the semester:

  1. Automate the interactions between the flocculation and sedimentation tank to integrate with the automated design code over a range of flow rates.
  2. Automate the plant leveling tank and determine hydraulic profile for each system in the plant.
  3. Developing the design algorithm for the baffle spacing to be used on Tamara plant.
  4. Develop further the Flow Control Module to design an algorithm as a function of desired chemical flow rate and the viscosity of the chemical.

A detailed account of timelines for our Spring 2008 Goals: