Semester Goals

Task

Completion Date

Finish Updating the Wiki

2/10

Edit/work on Mathcad code

2/13

Obtain Materials for experiment and location for Exp. set-up

2/18

Run First Experiment (2 trials per week)

2/25

Two more tests

3/3

Two more tests

3/10

Write up Mid-term results

3/14

Analyze Results compared to Computer expectations

3/28

Work on Mathcad to mimic exp. results

4/4

Run two more tests

4/11

Run two more tests

4/18

Complete Rough draft fo Final

4/25

Final Due

5/2

My initial estimation for building and installation of the entrance tank where too ambitious. It took me much longer to get the entrance tank installed and the pilot plant modified to accomodate the new entrance tank. I hope to make up for the time loss by running 4 tests per week after spring break.