You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 17 Next »

Abstract

A sedimentation tank is planned to be connected in series to the flocculator at the pilot plant. This sedimentation tank will allow us to isolate the process in the AguaClara design that needs to be optimized to allow us to achieve our overriding goal of consistently producing water under 1 NTU. Building this sedimentation tank allows for us to test not only the flocculation process but the sedimentation tank for design efficiency. Testing will include not only the traditional lamella design of sedimentation tanks but also the alternative of sludge blanket based sedimentation tank designs. These two processes will be tested side by side in parallel flow sedimentation tanks.

Introduction

The pilot plant sedimentation tank will be a vertical flow style tank and will only use a sludge blanket as its removal mechanism. This tank will be the first time that an AguaClara team has used a sludge blanket instead of plate settlers. As with other AguaClara designs, the tank will be run by the elevation head in the flocculator tank and will not require electricity. There are several design restraints due to the current set up at the pilot plant. There are 33.25'' of available water head at the end of the floculator which are available for our use. The piping connection between the flocculator tank and sedimentation tank also cannot have a shear value that exceeds the max shear in the last baffle section ( GMax= 48.826 /s), or else the flocs made in the last section will be broken up.  

Sludge Blanket Sedimentation Tank Design

The design of the tank was done during the Spring 2008 semester. The sedimentation tank was designed to be contained in a polyethylene tank of dimensions 24" x 24" x 36" (length × width × height) with a wall thickness of about 5/16". The design goal was to have enough area in the tank to create a sludge blanket. With the available water level height, which is taken directly from the water level in the floc tank, we did not have enough room to include plate settlers. Initially we wanted to split the plant flow rate (110 L/min) in half, allowing us the possibility of installing two parallel sedimentation tanks for experimentation purposes, but we found that a flow rate of 55 L/min into the tank would require a 6 inch pipe to transport water from the floc tank to the sedimentation tank to avoid breaking up flocs. Due to cost restraints (a six in bulk head fitting would cost about $300) we had to limit this pipe to being 4 inches, and we did that by lowering the flow rate of the sedimentation tank down to 24.5 L/min. This constraint on the inlet pipe and flow rate required us to switch to a smaller tank than originally planned. This change was necessary to obtain an upward velocity of 100m/day. This low flow and smaller tank set-up will allow for parallel testing of tanks containing different sedimentation processes.

Given Variables:

  • Length (L) = 23.125"
  • Width (W) = 23.125"
  • Height (H) = 36"
  • Water Level (WL) = 33.25"
  • Flow Rate (Q) = 24 L/min

Below is an AutoCAD drawing of the proposed sedimentation tank design.

!Pilot Plant Construction and Research^CAD drawing of sed
tank.jpg!

Below is a table of the calculated pipe dimensions and other calculated design parameters. The method behind each number can be found in the following design.

Parameter

Value

Inlet Pipe

4 in

Launder Diameter

1.5 in

Number of Holes

15

Hole Diameter

19/64 in

Tank Drain Diameter

0.75 in

Number of Holes

15

Hole Diameter

9/64 in

Leveling Outlet Pipe Diameter

3in

Weir Height

5cm below sed tank WL

Hopper Removal Diameter

0.5in

Hopper Removal Line Length

2m

Upward Velocity:
The upward velocity parameter determines what size of floc particles are removed from the sedimentation tank. Thus in order for our design to be comparable to exist sedimentation tank design Vup needs to be the same. Vup was set to be 100m/day. From this we calculated the flow rate through the tank was necessary to achieve this Vup.
Given there are no lamella the equation is fairly straight forward.

Unable to find DVI conversion log file.

From this equation the flow rate was determined to be 24 L/min.

Inlet Pipe Calculations:
To determine the diameter of the inlet pipe we used the constraint that the maximum shear due to minor losses had to be less than Gav in the last section of the flocculator (Gav = 24/s). The predominant minor losses from the inlet pipe will occur at the exit point and the elbow. The minor loss coefficient for the elbow is 0.9 and the exit is 1.0 so K was set to be 1.0 for this design. The equation to calculate shear due to a pipe elbow is shown below. This equation is solved for D, the diameter of the pipe that would provide shear equal to Gav. The equation used is very similar to the equation used to find the baffle spacing for the flocculator.

Unable to find DVI conversion log file.

Variables:
K = 1.0 (minor loss for an exit)

  • This equation was derived from a series of substitutions that can be seen above.
  • The head loss term that is found in the above derivation is assumed to include only minor losses. The minor head loss for this pipe is assumed to be the dominating factor because the pipe is designed to be relatively short in length and the bends and exit are our major sources of shear, the primary locations where floc break up would occur.
  • The velocity equals Q/A for the pipe.
  • The residence time term is found to be the volume over the flow rate through that volume.
  • The volume used was assumed to be the cross sectional area of the pipe times 2 diameters of the pipe.

Note: Initially during preliminary design with a large tank, we were using 55 L/min as the plant flow rate, and MathCAD returned that the pipe diameter would be 5.11 inches to achieve the desired Gav value. Due to the cost of 6 inch bulkhead fittings (nearly $300), we had to find an alternative design. We decided to lower the flow until a pipe with inlet diameter equal to 4 inches was achieved. We found that the maximum flow for these conditions is 24 L/min, so we changed the flow rate of the sedimentation tank. The option of multiple inlets was considered but this was discarded because then 2 - 4 bulk head fittings would be needed. Thus, the overall flow of the tank was lowered and a smaller tank was chosen. This change in flow rate necessitated a change in tank size (to a smaller cross sectional area).

Launder Calculations:

Pipe Diameter
The effluent launder will span the length of the tank about 4in off of center of the tank. The launder is placed 2 in beneath the water level. This value was assumed to be constant to allow for uniform flow through all of the launder orifices. The diameter of the effluent launder was calculated by iterating through pipe diameters to find the existing diameter of pipe that gave the desired flow rate and orifice holes. The diameter was selected based on the following equation:

Unable to find DVI conversion log file.
  • Qratio is assumed to be 0.90, this indicates that flow through the first orifice will be 90% of the flow through the last orifice.
    The best pipe diameter is 1.5 inches. The number of orifice holes was tweaked until the orifice hole diameter would match up with a drill bit size and still gave the proper amount of head. (equations for this can be seen in the following section) This head loss was defined to be about 5 cm, or the head available above the launder. If the head loss through the launder orifices exceeded the available head, we would have encountered issues because the water in the outlet system would have had less energy than the surrounding system, which would have effected the flow rate and caused air to collect in the outlet pipe. The total number of orifices was determined to be 15.

Orifice Diameter
The orifice equation was used to determine the necessary area of the orifice that gives the correct amount of head and matches with an existing drill bit size. The flow rate used in this equation was the total plant flow rate divided by the number of orifices. The minor loss coefficient for an orifice is assumed to be 0.63. The head loss term in the equation is total head available less the head loss in the manifold pipe less the velocity component of head loss through the pipe.
This area, was then converted into a diameter. This value was a rounded to the next smallest drill bit size. The diameter of each orifice was figured out to be 19/64".

Unable to find DVI conversion log file.

Orifice Head Loss
The head loss due to the orifice is an important parameter because it effects how evenly the water will flow through the orifices. Thus we back calculated the actual head loss achieved given the diameter adjustment that was made to achieve an existing drill bit size.
The head loss through the orifice was calculated by using the following equation:

Unable to find DVI conversion log file.

D is the diameter of the orifice (19/64 in), the minor loss coefficient of the orifice is 0.63, and the flow is the flow through one of the orifices. The minor loss for an orifice was calculated to be 4.54 cm. The head loss through an orifice is parallel to other orifices, so you do not add the head loss in each orifice. This parameter is the level that the water in the plant leveling tank needs to be below the water level in the sed tank in order for our plant to be operated at the designed water levels.

Secondary Outlet from the Flocculator
The flow rate of the sedimentation tank is designed to be 24 L/min, but the plant flow rate is designed to be 110 L/min. This means that excess flow needs to bypass the sedimentation tank and go directly to the outlet. A large outlet weir is our proposed design for the alternative exit. Because the head loss out of the sedimentation tank is relatively high (5cm through the manifold) the height of the water in the tank versus the weir height is assumed negligible(on the order of mm).

Since the flow rate into the floc tank has been measured to be anywhere between 70 L/min to 110 L/min, It was important to check whether the height of water in the floc tank could change enough to effect the flow rate to the sedimentation tank. If the accessory weir is required to take in a smaller flow rate, the water height in the floc tank will lower. This is the equation that describes the water height above the weir as a function of the flow rate.

Unable to find DVI conversion log file.

Where Cw is a constant (equal to 0.611+0.075*(H/Pw) where H is the height of water above the weir and Pw is the weir height), Q weir is the plant flow rate minus the sed flow rate, and the available perimeter was set to be 120 cm. In order to minimize changes in the floc tank the perimeter will be established by cutting a pipe laterally and letting water flow over the the cut out, down into the trough and then out the existing 3" outlet. When this was calculated we got a water height above the weir of 7.6 mm, which is small enough when compared to the head loss in the launder to assume that it will not affect the flow rate into the sedimentation tank.

Hopper Design for Sludge Blanket
Given the calculated amount of sludge the tank will create, a continuous sludge drainage system was created. This was done to decrease the size of the hopper in the tank. It was desired to keep the hopper small so that there would be minimal disturbance in the tank. We created a parameter, PhiFloc, which is the ratio of how much the alum flow rate relates to the the volume of flocs created in a certain amount of time. The value (0.016) was taken from the mathCAD file used to create the ideal Gmax versus Gtheta curve. The majority of a sludge is assumed to be made of alum, and the flow rate of alum is approximately 20 mL/min. Therefore, the rate of sludge build-up is the sedimentation flow rate times PhiFloc.

Unable to find DVI conversion log file.

When calculated, the sludge volume accumulated over two days was determined to be 1.105 x 10^3 L. We have decided to create this hopper with a conical funnel with flex-hose connected at the bottom. This small funnel will continuously drain sludge out of the tank and into the outlet panel. The hose will be 2m long and 1/2" in diameter. The diameter was determined using the manifold equation used in the design of the effluent launder design.

Plant Leveling Tank
The plant leveling tank will handle the outflow from both the sludge blanket tank and the plate settler tank. Using one leveling tank and identical inlet and outlet piping for the two tank ensures identical flow (assuming that the head loss through the tanks themselves are negligible). We decided to make the head loss into the leveling tank the dominant head loss through the system, which then sets the flow rate through the sedimentation tanks. Our design for the outflow system was an elevated 3'' pipe with an orifice set into the pipe below the water level. Using the orifice equation, with the flow set at 24 L/min, and using a predetermined safety factor of 18, a desired head loss of 13.673cm was found by multiplying the height of water over the weir in the floc tank by the safety factor. This head was used to determine the orifice size (7/8"). The orifice equation used was the same as used for the flocculator outlet but converted to a circular perimeter from a rectangle.

Tank Drainage Manifold
In order to allow for the entire tank to be drained of water quickly a tank drainage system was established. This system was designed to be very similar to tank tank systems used in Honduras. The set is basically equivalent to the effluent launder except this manifold is located at the bottom of the tank. Flow rate was set to allow the tank to drain in 30 minutes.

Unable to find DVI conversion log file.

This flow rate was established to be 19.425 L/min.
By the same method as was used for the tank effluent manifold the manifold diameter was determined to be 0.75" and the orifice diameter is 9/64".

  • The available head the available head for the sludge ports is the total water depth (33.25") minus the head loss in the manifold and minus the velocity head at the end of the manifold.
  • Kminor was assumed to be 0 in the manifold and 0.63 in the orifices.
    *Qratio = 0.90
  • 15 orifices were assumed to be uniform with the effluent manifold.

Results

The first sedimentation tank containing the sedimentation tank has been constructed. Flocs are entering the tank and not breaking up upon entrance so it has been determined that our entrance pipe calculations are reliable. Over the next week we are observing the tank and trying to see how the sludge blanket forms.

Design of the Sedimentation tank with Lamella

The same tank size was used for the lamella design as was used for the sludge blanket design. The lamella were designed to be constructed in a grid versus the plate lamella used in previous designs. This was done to ensure that a Vup of close to 100 was met.

The inlet design, the effluent launder design, tank drain design will all be the same as for the sludge blanket sedimentation tank. The only difference is that the inlet will have to enter the tank below the lamella and thus two 22.5 degree angle bends are to be used to lower the inlet pipe level from where it exits the floc tank to where it needs to enter the sedimentation tank. This tank was designed to be versatile and the lamella placed close enough to the top of the tank to allow for the possibility that a sludge blanket could be formed underneath the lamella if desired.

Lamella Design
The lamella were designed out of corrugated plastic. Flow was designed to move upward through the grid of channels in parallel. The dimensions of the material proposed for use are listed below.

  • b = 10.5mm - the distance between corrugations
  • w = 6.96mm - the width of the channel (same as the width of the material)
  • thickness = 0.40mm - the thickness of the plastic material
  • alpha = 60 deg
  • epsilon = 0.003mm

The first step in the lamella design was to determine the size of the lamella needed. A method very similar to the the one used to determine the correct pipe size for the effluent launder was used to find length of the lamella. The equation for lamella length is implicit and thus the correct length was iteratively determined.
The implicit equation used can be seen below:

Unable to find DVI conversion log file.

The following two equations were substituted into the above main equation.
Number of lamella sheets needs to fill the tank:

Unable to find DVI conversion log file.

The number of cells in on sheet of lamella given the tank size:

Unable to find DVI conversion log file.

The target Vup value was 100m/day. This was left constant instead of being updated with each iteration. This was done because the program would not converge otherwise. After the program returned the converging value of Lamella Length, the active upward velocity and critical upward velocity needed to be calculated. The active upward velocity is different from the target upward velocity because the dead zone created from the lamella angle has to be taken into account. The active length of Lamella, active upward velocity and critical velocity were calculated using the following equations:

Insert equation for active length of lamella.

Unable to find DVI conversion log file.


Unable to find DVI conversion log file.

The initial program of used to determine the lamella length returned the total length of the material placed at an angle of 60 degrees. For construction uses and determination of the inlet position we needed to determine the vertical height of the lamella. For this calculation the follow was used:

Unable to find DVI conversion log file. Unable to find DVI conversion log file.

Dimensions

Resulting Values

Lamella Length

13.717cm

Vup Active

128.027m/day

V critical

19.233m/day

Vert. Lamella Height

11.879cm

tot. Num. Sheets

75

Active Lamella Length

0.519m

Num. Active channels per sheet

39

Conclusions

  • No labels