Design Meeting Minutes

Summer 2009 Minutes

7/24/2009

Accomplishments
  • Changed the sed weirs to be the entire length of the inlet and exit channels and coded the autocad code.
Goals for Upcoming Week
  • Work on final presentation, indiviudal contribution pages, challenges for next semester.

Horizontal Flow Group

Accomplishments
  •  
Issues
  •  
Goals for Upcoming Week
  • Floc Hopper Group

Accomplishments
  •  Fixed the lamella orientation so that the lamella are angling away from the entrance channel, as opposed to originally being angled towards it.
  • Added to MtoA code so that floc hoppers will be arrayed the number of sedimentation bays within the tank.
Issues
  •  Still need to place the floc hoppers within the plant.
  •  Must add the MtoA floc hopper code to the sedimentation tank with pieces file when we are completed with it.
Goals for upcoming week
  •  Place floc hopper within plant, and add MtoA code to sed tank with pieces file.
  •  Update wiki page with final notes about floc hopper design and placement.

Floc Tank Group

Accomplishments
  • slots are drawn in the floc tank, and baffle widths are adjusted accordingly
  • L.slot is now a basic input (the depth of the slot) set to a default of 5cm
Issues
  • the up/down orientation of baffles in the last channel is backwards
  • the length of the baffles do not seem to be correct
Goals for upcoming week
  • meet with Monroe to determine the fate of baffles that coincide with the exit channel
  • correct baffle orientation in the last channel
  • correct baffle lengths

Materials List Group

Accomplishments
  •  
Issues
  •  
Goals for upcoming week
  •  
  • No labels