Design Meeting Minutes
Summer 2009 Minutes
7/24/2009
Accomplishments
- Changed the sed weirs to be the entire length of the inlet and exit channels and coded the autocad code.
Goals for Upcoming Week
- Work on final presentation, indiviudal contribution pages, challenges for next semester.
Horizontal Flow Group
Accomplishments
Issues
Goals for Upcoming Week
Accomplishments
- Fixed the lamella orientation so that the lamella are angling away from the entrance channel, as opposed to originally being angled towards it.
- Added to MtoA code so that floc hoppers will be arrayed the number of sedimentation bays within the tank.
Issues
- Still need to place the floc hoppers within the plant.
- Must add the MtoA floc hopper code to the sedimentation tank with pieces file when we are completed with it.
Goals for upcoming week
- Place floc hopper within plant, and add MtoA code to sed tank with pieces file.
- Update wiki page with final notes about floc hopper design and placement.
Floc Tank Group
Accomplishments
- slots are drawn in the floc tank, and baffle widths are adjusted accordingly
- L.slot is now a basic input (the depth of the slot) set to a default of 5cm
Issues
- the up/down orientation of baffles in the last channel is backwards
- the length of the baffles do not seem to be correct
Goals for upcoming week
- meet with Monroe to determine the fate of baffles that coincide with the exit channel
- correct baffle orientation in the last channel
- correct baffle lengths
Materials List Group
Accomplishments
Issues
Goals for upcoming week