Summer 2009 Minutes
7/3/2009
Accomplishments
- Changed chimneys in sed tank
Floc Hopper Group
Accomplishments
- A summary of major work completed since last meeting based on last meeting's identified outcomes/issues
-
Issues
- Difficult and unresolved issues
- Plans for action
Goals for upcoming week
Floc Tank Group
Accomplishments
- Exit port is now where it belongs
Issues
- The number of baffles in the last channel must now be an even number
Goals for upcoming week
- Ensure that the number of baffles in the last channel is an even number
- Draw slots to slide the baffles into
Exit Channel Group
Accomplishments
- A summary of major work completed since last meeting based on last meeting's identified outcomes/issues
-
Issues
- Difficult and unresolved issues
- Plans for action
Goals for upcoming week
Materials List Group
Accomplishments
- A summary of major work completed since last meeting based on last meeting's identified outcomes/issues
-
Issues
- Difficult and unresolved issues
- Plans for action
Goals for upcoming week