Accomplishments
- Went over Monroe's MathCAD algorithm
Spring 2009 Minutes
"2/20/09"
Accomplishments
- Went over Monroe's MathCAD algorithm
Outcomes
- Sara updated variables and parameters for the Gracias plant.
- Reviewed and updated team goals list based on Nicole's comments.
- Heather R & Adela continue working on a design for Gracias.
- Reiko & Heather H continue working on a design for the Ecuador plant.
Issues
- For next week, begin working on a materials list.