Design Goals
Fall 2008 Team Members
Reiko Baugham
Sara Schwetschenau
Cherish Scott
Tania Quesada
Fall 2008 Goals
- Overall Goal – continue to improve the automation of the design with built in checks for reasonable values ie. When can sed tank water depth be lowered from the 2m design.
- Whole Team to be divided as issues are encountered
- Aid Honduras Team with individual plant designs as they are presented to us
- Whole Team to be divided as issues are encountered
- Explore other methods of designing the sedimentation tank. Should b be set?
- Sara
- Adjust baffle placement in the flocculation tank for odd numbered baffles
- Tania
- Create design pages for sample tanks at different flow rates. For flow rates from 50 gal/min to 1200 gal/min in 100 gal/min increments. Pages will note what portions of the design aren't automated and recommend values.
- We will be working in pairs initially for these, but will split off for efficiency in 1 month.
- To be completed by Oct. 15
- Documenting Design Algorithms on the Wiki -
- Sara - Lamella, Sedimentation, Slopes, Exit Channel
- Tania - Math Functions, Pipe Database, Inlet Channel, Fluids Functions
- Cherish - User Inputs, Design Assumptions, Entrance Tank, Minor Loss Coefficients
- Reiko - FCM, Fluids Functions, Launder, Sludge Drain
(Note: bulleted points describe division of tasks)
You can find our teach in presentation here