Pilot Plant Sedimentation Tank Meeting Minutes
Fall 2008 Minutes
September 18, 2008
Accomplishments
* Julia and Kellie finished caulking the pipes.
* Team reviewed wiki pages.
* Team met at pilot plant on 09/18/08.
* Julia discussed with Sarah the configuration of the tube flocculator and the alum dose needed to form a floc blanket over time.
* Team goals for the semester were updated.
Outcomes
* Could not fully start up the plant because some of the caulk is not dry.
* Much of the sludge build-up was pumped out of the tank.
* Work on the wiki page was discussed and divided up among the sub-teams. Christine will work on the Tube Flocculator pages, while Kellie and Shaina rearrange different parts of the Sedimentation Tank page.
Metrics
* N/A
Issues
* Our method for pumping sludge out of the tank is unnecessarily time-consuming. We will try to find a different way.
* Since we could not start up the plant, Shaina will return on 09/19/08 to check the caulk and begin the running the plant with a 20 mg/L alum dose if the caulk is dry. We need to run the plant consistently at this concentration for some time before we can form a floc blanket.