Completed Plant in Tamara, F.M.
Inauguration, June 15, 2008
Parts of the Plant
Entrance tank
Flow measurement device
Chemical stock barrels (2 for aluminum sulfate, 2 for chlorine)
Flocculation tank, canal and sedimentation tanks
Sedimentation tank with effluent launderer
End of effluent launderer and foam removal tube
Hoses to sample each sed tank effluent
Chlorine application in exit tank
Clean-water tap from exit tank to fill chemical barrels
Underneath the platform
Tee in plant exit pipe (water either sent to tanks or to waste as controlled by a valve in the background)
Box with valves to clean flocculation and sedimentation tanks
Cleaning valves
Open box where all wastewater goes
Distrubution box divides plant effluent between 3 storage tanks
Storage and distribution tanks
Chemical storage room
Turbidimeter
Chalkboard to post water quality in community
Hydrualic latrine