AguaClara Five Year Plan

August 2007 to August 2008

Task

Location

Start

End

Document performance of Ojojona

Honduras

9/2007

ongoing

Build the water treatment plant at Tamara

Honduras

1/2008

4/2008

Train the Tamara plant operators

Honduras

5/2008

7/2008

Select next candidate communities for construction in Honduras

Honduras

2/2008

4/2008

Document Tamara plant performance

Honduras

5/2008

 

Latin America Network Workshop

Honduras

6/2008

6/2008

Hire Program Coordinator

Cornell

6/2008

6/2008

Identify the funding mechanism for the next communities

Honduras

6/2008

8/2008

AguaClara team provides detailed designs for APP selected communities

Honduras

6/2008

6/2008

August 2008 to August 2009

Task

Location

Start

End

Build 5 water treatment plants

Honduras

8/2008

8/2009

New Regional Partners assess potential community sites

Latin America

8/2008

10/2008

Latin America Training Program for engineers and technicians

Honduras

9/2009

10/2009

AguaClara team provides detailed designs for Latin America communities

Cornell

10/2008

12/2008

Latin American partners design plant for first communities

Latin America

1/2009

2/2009

Latin American partners build plant for first communities

Latin America

3/2009

7/2009