9/22/08-9/28/08

Sedimentation

Accomplishments

  • Read the wiki to get a better grasp of the project
  • Prepared for the teach-in for Tuesday
  • Went to the plant (9/25) to discuss potential solutions to the leakage in the upflow bucket
  • Obtained 0.5" diameter caps for the lamella rods and the materials to seal the pipe to the sed tanks

Outcomes

  • Still unable to operate the plant due to leakage in the bucket that controls upflow velocity
  • Tom suggested replacing bucket with 12" diameter PVC pipe to prevent leaking
  • Will concentrate on wiki organization until plant is running again

Metrics

  • N/A

Issues

  • Bucket is leaking, even after multiple attempts to caulk, seal, and waterproof

9/15/08-9/21/08

Accomplishments

...