Task

Location

Start

End

Build 5 water treatment plants

Honduras

8/2008

8/2009

New Regional Partners assess potential community sites

Latin America

8/2008

10/2008

Latin America Training Program for engineers and technicians

Honduras

9/2009

10/2009

AguaClara team provides detailed designs for Latin America communities Latin America

Cornell

10/2008

12/2008

Latin American partners design plant for first communities

Latin America

1/2009

2/2009

Latin American partners build plant for first communities

Latin America

3/2009

7/2009

...