- Held a meeting with Monroe and the people in Honduras. It was a basic Q&A session and helped clear up a lot of things so we can proceed. (notes can be found on the Tasks page linked at the bottom)
Metrics
- Quantitative and qualitative results from accomplishments and outcomes.
- Potential metrics for unresolved issues.
Outcomes
- A summary of resolutions based on what was accomplished.
- New directions and ideas that result from these resolutions.
Issues
- Team members continued to work on their individual tasks.
Outcomes
- Decided that ports between channels will be located at the top of the wall instead of the bottom
- Sludge drain dimensions will be constrained so that they must be able to cover a 3-4" pipe
- The flocculator program has been changed & updated so each channel will have the same spacing. The channels have also been updated so the ports between channels match the spacing between baffles.
- This program is currently being reviewed by Monroe.
- A floc channel drain was also added to the program, as well as alternating ports on the bottom of the lower baffles for the tank to drain.
Issues
- Chemical stock tanks need to be changed so that a volume and dimensions are given. This will give engineers the option of using barrels or building tanks.
- In order to determine baffle thickness the baffle area needs to be included
- Difficult and unresolved issues
- Plans for action
Any Overall Team Comments:
...