Summer 2009 Minutes

7/17/2009

Accomplishments
  • Finished coding the new weirs at the end of the inlet and exit channels

Horizontal Flow Group

Accomplishments
  • Reviewed current code for flocculator
  • Noted any values that would potentially need to be changed to allow horizontal flow
Issues
  • What inhibits the design from just being an 'if' statement that for the most part rotates the tank 90 degrees?
Goals for Upcoming Week
  • Meet with Monroe to discuss ideas and more theory behind switch
  •  
  •  

Floc Hopper Group

  •  
Accomplishments
  •  
Issues
  • Worked more on MtoA code for floc hopper. Added array code and fixed incorrect code.
Issues
  •  Unsure of whether to place floc hopper at the entrance or the exit of the sedimentation tank.
  •  Still need to figure out correct placement of floc hopper. 
Goals for upcoming week
  •  Will email Monroe with our question about floc hopper placement.
  •  Finish the MtoA code. 

Floc Tank Group

Accomplishments
  • Discovered that ports are not in fact taking up the whole height of the floc tank, but rather are drawing in the negative direction
Issues
  • Baffle spacing is currently too small and must be changed so as to ensure the width and height calculations of the ports come out to be positive

...

  • Ensure that a minimum baffle spacing is achieved
  • Draw slots for the baffles

Materials List Group

Accomplishments

...

  •  
Issues
  • Made changes to wiki page based on Midterm report feedback
  • Corrected calculations for floc baffles and inlet chimneys
  • Finished calculations for all piping
Issues
  • The next step is pricing, but the pricing document is in Spanish. We contacted Monroe - Matt and Nadia plan to help us with this. 
Goals for upcoming week
  •  Finish task