Design Team Meeting Minutes
Spring 2009 Minutes
Friday, March 13, 2009
Accomplishments
- Updated algorithms for new geometries
- Sludge drain: change from pipe to channel
- Inlet channel: change from drop pipes to chimneys
- Entrance Tank algorithm now calculates dimensions of the tank and incorporates a grid chamber in the design
- Completed slopes program for sedimentation tank
- Updated Master Program to incorporate new designs
- Deleted any unnecessary information
- Added dimensions thought to be useful
Metrics
- Quantitative and qualitative results from accomplishments and outcomes.
- Potential metrics for unresolved issues.
Outcomes
- New programs need to be copied into the master file
- Current program/algorithm changes were made to the Gracias file; the programs need to be copied to all other designs
- Need a new page for Hopper algorithm
- AutoCAD can now be updated
Issues
- Need to make sure documentation is completed for program changes
- Continue checking code for variable name changes