Pilot Plant Meeting Minutes

Spring 2009 Minutes

February 6, 2009

Accomplishments

  • Went to Cornell Water Treatment Plant and did overview of pilot plant and functions
  • Went over Pilot Plant Quiz
  • Made preliminary designs for new baffle system and timeline to accomplish

Outcomes

  • Design one baffle for each of the proposed new baffle systems
  • Evaluate each baffle designed based on cost, ease of construction, and practicality
  • Produce baffle system of best design

Issues

  • Only building one baffle of each, but when we build the new system we may need funding
  • Do we have the materials currently to build new baffles?
  • We're testing different designs individually however so we don't end up wasting money on a design that we later decide is not the best
  • Flocculation tank is not in the best shape. Will need to strengthen the middle channel's walls