As the Unit Processes design subteam our Our main goal for the semester is to Successfully aid in the construction and completion of the Marcala Water Treatment Plant.
In order to achieve this goal we developed four sub-goals:need to:
- Communicate effectively with plant engineering concerning current plant development.
- Determine Baffle Spacing for Section A of flocculator.
- Specify Plant Leveling Tank Mechanics
- Calculate Dimensions of Effluent Launder from Sedimentation Tanks to Plant Leveling Tank
Once the final aspects of the Marcala Water Treatment Plant are designed, we will work to integrate our designs with the automated design team.