Pilot Plant Sedimentation Tank Meeting Minutes

Fall 2008 Minutes

September 29, 2008

Accomplishments

  • Some organization changes made to the wiki
  • Completed teach-in on Tuesday
  • Fabricated the seal to prevent water from going to the sed tank
  • New part came in to control the leakage in the upflow controller
  • Acquired new team member "Tom" from the Flocculator

Outcomes

  • Should be able to test the vertical flocculators now that the water cannot get to the sed tanks.
  • Class is now informed about the workings at the pilot plant, and we also have a better understanding.

Issues

  • Information from the wiki is hard to divide into the four headings.  Some overlap, but will try to finish that for next week
  • Still unable to experiment with the sed tanks, but that should change soon.
  • No labels