Linear Flow Orifice Meter Meeting Minutes

Fall 2008 Minutes

September 11, 2008

Accomplishments

  • Met with david railsback to go over his visions for how the project should progess as well as gain his insight into the project. At the time the summer team hadn't given us their information so we didn't have much specifically to talk about.I gave him an update on the progress made with the linear orifice flow meter spring 2008 and showed him the results.
  • Discussed the work done during summer 2008. they created a prototype of the lever arm for chemical dosing and nicole walked me through how their set-up works. We briefly talked about where we thought improvements could be made: stonger connecting medium (curretly fishing wire), thinner float so it will fit into the entrance tank, and stable support mechanism for the flow control modules.

Metrics

  • We also worked on combining our goals page, which we later found out was wrong and we should have two seperate pages.

Outcomes

  • We plan on meeting David again later this semester when we are caught up.

Issues

  • seperate goals pages needed
  • need to have meeting with Monroe to understand direction for this semester.