Plate Settler Spacing Meeting Minutes

Spring 2009 Minutes

2.27.09

Working Group: 1

Accomplishments
  • Began automating the system using the increment method in Process controller
  • Recoded the process controller program for floc blanket and effluent flow rate variation
  • Ran the system to test floc blanket formation
  • Added an elbow
  • Sucessfully floc blanket height using process controller
Metrics
  • None this week
Outcomes
  • We are continuing to debug our process controller method to automate the varying of flow rates
  • In the process of ordering a web cam to monitor floc blanket height. This will help us deterimine the time it takes to form a floc blanket.
Issues
  • When increment function restarts instead of starting at the minimum flowrate it starts at the maximum flowrate.
  • We need to do some test runs of the system to determine the necessary duration of each process controller state.

Any Overall Team Comments:

  • Most of the week was spent working with process controller. Next week we look forward to collecting data.