Design Team Meeting Minutes
Fall 2008 Minutes
October 6, 2008
Accomplishments
- Whole Team met to review the slope issues with the Gracias Design
- Worked through a variety of algorithms to determine what the best fix is
- Design code was updated and new slopes program made to reflect the necessary changes.
Outcomes
- More work still to be done to prefect the drawing programs, slope changes require a few drawing changes.
- Need to review 4 Communities design to check that slopes issues does not affect that design as well.
- Need to meet with Monroe again to check new slopes algoithm decided upon.
Issues
- Completely Automating these programs is proving difficult. Brainstorming ways to best automate the slopes program for automatic adjustment for any plant design.