Fall 2014 Syllabus
Check out these guides on assignments due throughout the semester:
Date | Class Topic | Research Work Due | Design Work Due |
1 W 8/27 | Class:Introduction to AguaClara, Subteam Overview, and Interview Signups Hollister 366 | Sign up for an Interview
Review How Water Flows Through the Plant
Read the Team Challenges Page
Complete the pre-interview form before your scheduled interview | |
Th 8/28 – Sat 8/30 | Interviews in the AguaClara Lab (Hollister B60 – in the basement). Interview results will be announced via email on Sunday evening. |
|
|
W 9/3 | Class: How Water Flows through the Plant, Administrative Essentials,Team Reveal Hollister 366
| Set up an event (coffee, lunch, etc.) outside of the lab with your subteam!
Set up a meeting with Research Advisor to go over challenges/apparatus before September 8 | |
F 9/5 |
| Complete the online lab safety training
Complete the AguaClara Technology quiz (retake until you get 100% correct) |
|
3 M 9/8 | Research: Team Work Design: Team Training | Sign up for trainings: Process Controller (with Casey Garland), Shop (with Tim Brock), |
|
W 9/10 | Research: Team Work Design: Team Training | New members: Create yourindividual wiki page Update your subteam’s wiki page Check out thewiki organization guide for more information on how to properly use the wiki |
|
F 9/12 |
| Design Trainings 1 and 2 due | |
4 M 9/15 | Research: Team Work Design: Team Training | Complete MathCAD Training |
|
W 9/17 | Research: Team Work Design: Team Training |
| Design Training 3 due |
F 9/19 |
| Complete all required trainings by today | Design Training 4 due and email Meghan with top 3 task choices |
5 M 9/22 | Research: Team Work Design: Team Work |
|
|
W 9/24 | Research: Team Work Design: Team Work |
|
|
F 9/26 |
| Research Report Due
Check-in survey due | Progress Report Due
|
6 M 9/29 | AguaClara LLC Presentation: Sarah Long Implementation Partner Presentation: Minty Hollister 366
| You should begin thinking about Symposiums
|
|
W 10/1 | Research: Team Work Design: Team Work |
|
|
F 10/3 |
|
|
|
7 M 10/6 | Research: Team Work Design: Team Work: Wiki Training |
|
|
W 10/8 | Research: Team Work Design: Team Work |
|
|
F 10/10 |
| Research Report Due
| Progress Report Due
|
8 M 10/13 | Fall Break- No class |
|
|
W 10/15 | Hollister 366 |
|
|
F 10/17 |
|
| |
9 M 10/20 |
|
|
|
W 10/22 |
|
| |
F 10/24 |
| Midterm Peer Evaluation Form Due
Update yourIndividual Contribution Page |
|
10 M 10/27 | Research: Team Work Design: Team Work |
|
|
W 10/29 | Research: Team Work Design: Team Work |
|
|
F 10/31 |
|
|
|
11 M 11/3 | Research: Team Work |
|
|
W 11/5
| Research: Team Work Design: Team Work |
|
|
F 11/7 |
| Research Report Due
| Progress Report Due
|
12 M 11/10 | Research: Team Work Design: Team Work |
|
|
W 11/12 | Research: Team Work Design: Team Work |
|
|
F 11/14 |
|
|
|
13 M 11/17 | Research: Team Work Design: Team Work |
|
|
W 11/19 | Research: Team Work Design: Team Work |
|
|
F 11/21 |
| Research Report Due
| Progress Report Due
|
|
|
|
|
14 M 11/24 | Research: Team Work Design: Team Work |
|
|
W 11/26 | Thanksgiving Break |
|
|
F 11/28 | Thanksgiving Break |
|
|
15 M 12/1 | Research: Team Work Design: Team Work |
|
|
W 12/3 | Research: Team Work Design: Team Work |
|
|
F 12/5 | Research: Team Work Design: Team Work | Peer Evaluations Due
Final Report Draft Due | Peer Evaluations Due
Final Report Draft due |
F 12/12 |
| Final edited report due Update yourindividual page and your team wiki page |
|
Sun 12/14 | Final Presentations, 3:00 PM – 8:00 PM | Upload final presentation to your subteam’s wiki page by 2:00 PM |
|
Grading Rubric
Research Teams and Design Team Rubric
Assignment | Weight |
First two progress reports | 5% each |
Final two progress reports | 10% each |
Symposiums | 10% |
Final report | 20% |
Final presentations | 20% |
Effort and progress towards goal (adjusted for each individual subteam member) | 20% |
Total: | 100% |
Public Relations Team Rubric
Assignment | Weight |
Written and oral work | 40% |
Symposiums | 10% |
Final Presentations | 20% |
Effort and progress towards goal | 30% |
Total: | 100% |