Help and Support:
Cornell's Current FOLIO Version: Kiwi Hot Fix 3
Orchid Maintenance schedule:
Critical service patch #6
- Training - COMPLETE
- Test - COMPLETE
- Production - COMPLETE
- eUsage and Open Access apps added to Prod COMPLETE
Poppy upgrade schedule (CSP-4):
- Upgrade Dry-Run: 1/25 COMPLETE
- Testing IN PROGRESS
- Upgrade Training: 4/26 PENDING
- Upgrade Test: 4/29 - 5/1 PENDING
- Upgrade Production: 5/3 PENDING
Quesnelia upgrade schedule:
Bugfest: April 2024 COMPLETE
LDP upgrade schedule:
Orchid Maintenance schedule:Critical service patch #6
| |
---|---|
Poppy upgrade schedule (CSP-4):
| |
Quesnelia upgrade schedule:Bugfest: April 2024 COMPLETE |