#Cuatro Comunidades
#Gracias
#Documentation Study
Cuatro Comunidades
Last week was Semana Santa so Antonio and Dan had only visited the treatment plant once. There are still details to complete including putting in the doors, cleaning the area around the plant, and finishing the caps on the walkway. Currently the chlorine doser is not installed in the plant and is still being applied in the distribution tank with the flow control module.
From Cuatro Comunidades Construction |
Gracias
Tamar and Eng. Wil visited Gracias on Wednesday 4.2 to evaluate the land where the plant is proposed to be built. The terrain will be easy to build into, similar to the plant in La Cuatro Comunidades. We hope to have the budget complete by April 17th.
Documentation Study
On Friday 4.3 we met to discuss the documentation study for AguaClara. With Daniel Smith now on board, he will be dedicating his time to help out with evaluating the plants. Jacobo is proposing to meet with Centro de Recursos to bring them on board to provide validation of our process.