Goals for Summer 2009
Summer 2009 team members
Summer 2009 Goals
- Rapid Mix Testing: We are attempting to recreate a surface film similar to that found in AguaClara Plants in Honduras in a lab setting.
- The group will work together and hopes to accomplish this within a three week period
Week 1: Varying Alum Dosage (35 mg/L, 45 mg/L, 55 mg/L, 65 mg/L)
Week 2: Varying Turbidity
Week 3: Varying Location of Alum Addition (above water surface vs below water surface)
- Non-Linear Dose Controller: We need to revise the MathCAD code before constructing a fully functional model.
- The group will work together and hopes to accomplish this after completing our first goal.
Week 4: MathCad Revision
Week 5: Construction of Level Arm
Week 6: Assembly of Non-Linear Dose Controller
Bibliography
- D. Bouyer, R. E. (2005). Experiemental Analysis of Hydrodynamics in a Jar-Test. Institution of Chemical Engineers , 22-30.
- D. Chapple, S. M. (2002). The Effect of Impeller and Tank Geometry on Power Number for a Pitched Blade Turbine. Institute of Chemical Engineers , 364-372.
- Johnson, D. E. (1996). Effect of organic matter on bubble surface tension. Journal of Geophysical Research , 3769-3774.