- Transfer the loads from CFD to FEA in Workbench
- Close Mechanical
- Drag the solution cell from the CFD project to the Setup cell of the FEA project
- Double-click on physics setup to go back in mechanical and update the upstream data when prompted.
- Import the pressure in Mechanical
- The imported load solution folder will appear in the tree outline. Right-click it and select insert pressure.
- For the top field, select the blade surface from FEA the wetted surface.
- For the bottom field, select the blade surface from CFD.
- Open the report and check how the forces match and if 100% of the nodes have been mapped.
- The imported load solution folder will appear in the tree outline. Right-click it and select insert pressure.
Go to Step 5: Numerical Solution
...