  • The tanks at the end of the inlet and exit channels that hold the pipes leading to the distribution tanks and to the waste no longer need to be as tall as they are currently drawn. Rather they can just cantilever off the side of the sedimentation tank. Also the pipes in these tanks that lead to waste should be drawn as Tee's that connect to one another and then lead to waste.
Sedimentation Tank Control Pieces
  • The pieces that allow the sedimentation tanks to be shut off need to be drawn (caps for the inlet channels, and exit channels). In addition, the caps should have a 1" PVC pipe that extends above the surface of the water in order to prevent air being trapped in the pipes delivering flocculated water to the sedimentation tank, and also to serve as a handle for removing the caps.
Material's List
  • This list has been started and needs to be edited with input from the engineers in Honduras.

...