After consulting with engineer Wil Serrano, the ports between the flocculator channel need to be switched from the bottom of the tank to the top. From a structural perspective it is much better to be able to tie the walls together at the top of the wall.

Baffle Spacing and Exit Port
May, Lindsey--7/8/09 tentative

...

This code needs to be heavily edited and brought into compliance with the variable naming protocol.

Entrance tank

A first draft of this code has been created, but it has not yet been reviewed.

...

These tanks need to be drawn. These may be an item that the onsite civil engineer will relocate to fit site conditions, but the design tool should show them at the correct elevation and in a reasonable location.

Materials List

Andrew, Nanditha - Est Completion Date 6/30/09

...