Plate Settler Spacing Meeting Minutes
Spring 2009 Minutes
2.20.09
Working Group: 1
Accomplishments
- Added floc blanket control valve and extended outlet into column to control height.
- Extended bubble trap tube.
- Rotated sedimentation tubes 90 degrees.
- Completed revision of semester goals
- Met with Monroe to improve system design and dicuss experiments.
Metrics
- Kellie updated the mathcad file to include calculations of flow rates based on our Vc range
Outcomes
- Need to update process control to include incrementation and a new state to change flow rates
- Need to order new tubes with larger diameters
Issues
- Process Controller
- Need to make a schedule to moniter the system
- Camera?