Pilot Plant Meeting Minutes

Spring 2009 Minutes

February 13 2009

Accomplishments

  • Finished design for new baffle system
  • Revised goals based upon Monroe's and Nicole's comments as well as through disscussion within the group.
  • Finalized meeting times for the semester

Outcomes

  • Meeting with Monroe on Friday to discuss revised goals and new baffle design.

Issues

  • None of us are familiar with FReTA
    • Research and discuss with Monroe about FReTA
  • Can our design be accomplished within time constraints?
  • Need a detailed procedure for measuring turbidity profiles.