On Wednesday 1.28 we decided on where the plant would connect the pipe to the distribution line going into the distribution tanktank would leave the plant. We also confirmed the plant levels on of the ground walkway around the flocculation and sedimentation tanks.

Antonio also did a complete inventory of the products construction materials left in storage. There is a form that the president of the Junta, Jorge was supposed to be in charge of monitoring all updating. All the materials entering and leaving the storage shed are noted on the form. However, since sometimes he Jorge is not there when construction is taking place, some of the information is missing.
Antonio had the chance to reaffirm the importance of transparency and keeping track of materials. This will also help the AguaClara team compare what was used with what was originally budgeted.

...