Linear Orifice Flow Meter

...

Goals

...

Task

...

Completion Date

...

Finish Updating the Wiki

...

2/10

...

Edit/work on Mathcad code

...

2/13

...

Obtain Materials for experiment and location for Exp. set-up

...

2/18

...

Run First Experiment (2 trials per week)

...

2/25

...

Two more tests

...

3/3

...

Two more tests

...

3/10

...

Write up Mid-term results

...

3/14

...

Analyze Results compared to Computer expectations

...

3/28

...

Work on Mathcad to mimic exp. results

...

4/4

...

Run two more tests

...

4/11

...

Run two more tests

...

4/18

...

Complete Rough draft fo Final

...

4/25

...

Final Due

...