Fall 2008 Minutes

10/09/08

Accomplishments

  • Collaborated Worked with Matt to setup of the systemexperiment apparatus.
  • Drilled the approiate holes for in the bucket sytem for the clay and water mixture.
  • Determined what are materials are need still needed to complete the system.
  • Danny created a connector for to connect the manifold to a smaller tubingthe tube carrying away the effluent.

Outcomes

  • Continue Continued to document the setup process (diagrams).
  • Almost completed setting up setup of the whole experiment model.

Issues

  • Need help to install the pinch value.
  • Need to gather more materials for the setup.