AguaClara
...
Three Year Plan
August 2007 to August 2008
Task | Location | Start | End |
---|---|---|---|
Document performance of Ojojona | Honduras | 9/2007 | ongoing |
Build the water treatment plant at Tamara | Honduras | 1/2008 | 4/2008 |
Train the Tamara plant operators | Honduras | 5/2008 | 7/2008 |
Select next candidate communities for construction in Honduras | Honduras | 2/2008 | 4/2008 |
Document Tamara plant performance | Honduras | 5/2008 |
|
Honduras | 6/2008 | 6/2008 | |
Hire Program Coordinator | Cornell | 6/2008 | 6/2008 |
Identify the funding mechanism for the next communities | Honduras/Cornell | 6/2008 | 8/2008 |
AguaClara team provides detailed designs for APP selected communities | Cornell | 6/2008 | 6/2008 |
August 2008 to August 2009
Task | Location | Start | End |
---|---|---|---|
Build 5 water treatment plants | Honduras | 8/2008 | 8/2009 |
New Regional Partners assess potential community sites | Latin America | 8/2008 | 10/2008 |
Latin America Training Program for engineers and technicians | Honduras | 9/2009 | 10/2009 |
AguaClara team provides detailed designs for Latin America communities | Cornell | 10/2008 | 12/2008 |
Latin American partners design plant for first communities | Latin America | 1/2009 | 2/2009 |
Latin American partners build plant for first communities | Latin America | 3/2009 | 7/2009 |
Selection process for second launch site | Global | 2/2009 | 6/2009 |
August 2009 to August 2010
Hold a regional workshop in Latin America to share experiences and to develop improved strategies.
Send AguaClara Engineers to second launch site. Send team from regional partner at second launch site to Latin America to learn from experiences and to see construction projects and operating AguaClara plants.