The Marcala plant upgrade to 55 L/s was completed a few months ago. That plant is serving 15,000 people and brings the total population served by AguaClara facilities to 25,000!
The Alauca plant construction is proceeding very rapidly. You can see photos of the construction on our Picassa site (https://picasaweb.google.com/CUAguaClara/AlaucaProjectImage Removed).
The Atima project is proceeding through the pre-construction phases. It has Rotary approval and it is expected to move into construction soon.

...