Design Meeting Minutes
Summer 2009 Minutes
7/3/2009
Accomplishments
- Changed chimneys in sed tank
Floc Hopper Group
Accomplishments
- Created the wiki page for the floc hopper, along with the inputs and outputs pages.
- Continued work on MtoA code for floc hopper design.
Issues
- Had trouble getting our MtoA code to output a correct text file.
- Will consult Heather or Monroe at meeting on Tuesday to correct this problem.
Goals for upcoming week
- Complete MtoA code on the actual floc hopper design.
Floc Tank Group
Accomplishments
- Exit port is now where it belongs
Issues
- The number of baffles in the last channel must now be an even number
Goals for upcoming week
- Ensure that the number of baffles in the last channel is an even number
- Draw slots to slide the baffles into
Exit Channel Group
Accomplishments
- Program has been completed and documented
- Necessary information as well as AutoCAD renderings are available on the Wiki
- Tested and functioning
Materials List Group
Accomplishments
- Created wiki page for Materials List
- Created Input and Outputs pages for Materials List
- Finished all plant and channel walls
- Worked on calculations for Sed Plate Frame and other pipe components
Issues
- Had trouble understanding some of the pipe and valve components
- Had to figure out how to create, format, and publish a new wiki page with MathType and Inputs and Outputs
Goals for upcoming week
- Work on pipes and find out more information about pipes and valves that go between channels
- Find dimensions and calculate volumes for Inlet Channel chimneys, weirs, and channel tanks