Plate Settler Spacing Meeting Minutes
Fall 2008 Minutes
10/09/08
Accomplishments
- Worked with Matt to setup experiment apparatus.
- Drilled holes in the bucket for the clay and water mixture.
- Determined what materials are still needed to complete the system.
- Danny created a connector to connect the manifold to the tube carrying away the effluent.
Outcomes
- Continued to document the setup process (diagrams).
- Almost completed setup of the experiment.
Issues
- Need help to install the pinch value.
- Need to gather more materials for the setup.
{"serverDuration": 65, "requestCorrelationId": "6b95ce2456ecdeae"}