Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Sara and Kevin met at the plant today. Kevin calked the bottom panell panel of the tank to prevent upwelling during operation. Caulking the bottom adequately is very important because if it does not seal properly, then more time will be necessary to fix the problem. The walls were wiped down to make sure dirt or particles wouldn't effect the cohesion to the wall. Also, the edges were vacuumed to get dirt and water left over under the crack. This could also effect cohesion. Kevin also helped Tom cut the in-flow pipe in order to put in the flow meter. The flow meter was not fully installed because Tom had other stuff to do.  Sara refitted the baffle connections in section 2 since we noticed that many of the connections were loose or broken.

February 30,2008

Dave went to the plant today to refit the baffle connections in section 1. 

Day

Task for Week of FEB 24-29

Monday

Alter turbiditimeter outlet to raise pressure; implement settling tube suspension system

Tuesday

Fix Baffles (loose screws etc)

Wednesday

Changing Rapid Mix to accommodate entrance tank

Thursday

Caulk the bottom panel of tank

Friday

Implement all changes and restart the tank

February 30,2008

Dave went to the plant today to refit the baffle connections in section 1.

March 3, 2008

Kevin and Dave went to the plant to try to get the plant running. However, the in-flow pipe had not been put back together (the flow-meter was supposed to be installed), as Tom had promised. Instead we figured out a way to support the in-flow bucket using metal braces. Decided on a design with Tom, and are going back tomorrow to work on it.