Sara, Dave, Leah and Rebecca met at them plant today. We installed the pressure head device and reconfigured the turbiditymeter tube set up. We made the pressure head device as tall as the room would allow, with the idea that we will re-fit it to the correct height once we have records of the temperature difference between the inflow water and the turbiditymeter vial. We discussed possible methods for suspending the tube settlers. We also reffited the inflow pump to allow for Leah's auto alum control device, which we will install once we get the parts on Monday. We also reviewed possible actions to take once the plant is running and made a rough outline for next week.  

February 29,2008

Sara and Kevin met at the plant today. Kevin calked the bottom panell of the tank to prevent upwelling during operation. Sara refitted the baffle connections in section 2 since we noticed that many of the connections were loose or broken.

February 30,2008

Dave went to the plant today to refit the baffle connections in section 1. 

Day

Task for Week of FEB 24-29

Monday

Alter turbiditimeter outlet to raise pressure; implement settling tube suspension system

Tuesday

Fix Baffles (loose screws etc)

Wednesday

Changing Rapid Mix to accommodate entrance tank

Thursday

Caulk the bottom panel of tank

Friday

Implement all changes and restart the tank