Sara - updating old papers up to the wiki. Work done on Teach-in Presentation. David- Finished draft of gannt chart

February 18, 2008

Entire group met at plant along with Leah to review plant data from the weekend and discuss options for the Automated flow device. Also reviewed options for insulation and lighting on McMaster, and came up with potential options. Sara also described testing procedure to the rest of the group and Rebecca cleaned the turbiditymeters. Plant results were inconsistent, and the turbidity in the flocculator continues to be larger then the inflow water. Heavy condensation was noticed on the tubes connecting the tube settlers to the turbiditymeters, indicating a significant temperature difference between the water and the air.