Challenges

...

  • All group members will be working on this for the week of Feb 9th

...

  • Each group member will have a design to build independently (Feb 16)

...

  • Rustom (Feb 22)

...

  • Full group (Feb 23)

New Baffle System

  • Build new baffle system that can be constructed quickly that allows for easy modification of baffles at the Pilot Plant
    • Subteams of two from the PP team will be constructing a row of baffles for each of the floc tank channels.
  • Install new baffles

Automatic Alum Dosing

  • Research affects of turbidity, temperature, pH, etc. on alum dosing
  • Determine formula for appropriate dosing based on above measures
  • Incorporate formula into Process Controller to automatically change alum dose with inflow raw water turbidity and temperature

Develop Flocculator Performance Curves

...

  • Run the plant, fix any leaks or problems
    • Art, Mike (after new baffle system is in place, early March)
  • Begin research on dose controller at the pilot plant and construct
    • Rustom, Lalo (beginning of March). Collaborate with dose control group.
  • Determine procedure for taking turbidity profiles
  • Collect turbidity profiles for different baffle arrangements and tapered vs. non-tapered arrangements
    • Art, Mike (this will be ongoing for several weeks)
  • Calibrate all turbidity meters (Ian has the standards)
  • Develop protocol for plant maintenance to ensure that collected data is not affected by dirty turbidimeters
  • Develop plan to set alum dose appropriately.
  • Compile data, analyze, graph results
    • Rustom

-FReTA Comparison_

  • Set up FReTA to be used with the tube flocculator and use to compare settling velocities at different points in the tube flocculator
    • Jeff (March). Collaborate with Ian.
    Compare raw water readings from the Pilot Plant FReTA with the laboratory results (three way comparison between CUWFP's flocculated water, the tube flocculated water, and the pilot plant flocculator)
    • Jeff
    • Jeff (March). Collaborate with Ian.
  • After completion of these challenges, formulate challenges for sedimentation tank and begin research there
    • Full group. After completion of aforementioned goals.

Bibliography

References for our project that our team has found in literature searches.

...

Submissions for end of semester

  • New, easy to construct, easy to adjust baffle system
  • Method for obtaining turbidity profilesAutoCAD drawing of new baffle design as well as picture of completed baffle system
  • Turbidity profiles of different baffle spacingsDocumentation of dose controller at Pilot Plantfor different baffle arrangements and for tapered vs. non-tapered baffles
  • Settling velocity data for Pilot Plant FReTa
  • Comparison of Pilot Plant FReTa results with lab results