Construction continues to progress well. Nearly all of the bricks are laid for the tank walls and they have begun to build the foundations for the chemical tables. The polycarbonate panels for the floc and sed modules arrived Thursday 12.11. Other miscellaneous materials should arrive later this week so that all is ready to begin assembling the modules when the students are here in January.

Image Removed Image Removed

After discussing with Monroe and the design team, we decided on the size of the floc lamella and arrived at a method for installing the plaques that will form the entrance manifolds in the bottom of the sed tanks.

...