Attendees

Sarah, Dan, Aaron H, Dave, Kevin, Rina, Butch, Tony, Steve S

Objective

Develop a schedule for execution of the work necessary to successfully launch the PPI-1

Notes

Bodies of work to content with:

  1. Communication
  2. Security, provisioning
  3. Identity Service Integration
  4. Data Conversion
  5. Data Mapping
  6. Environment(s)
  7. Batch Processing
  8. QA
    • Testing
    • Implementation and operations
  9. User Training
  10. ID&R and reporting
  11. Feedback

Communication

  • Identify stakeholders
    • Dave's contacts (users), liasions
  • Communicate launch, progress, schedule
  • User expectation setting
    • Validation process
    • Time and effort commitments
    • Issue vetting, response time
  • Roles and Tasks (who will do what)

Security, provisioning

  • Define roles (new PPI-1 role)
  • Identify users (see functional requirements document for current list, number may increase)
  • Alter data conversion (impact to be assessed)
  • No workflow
  • Testing
    • Can users do what they need to do?
    • Can users NOT do what they are not supposed to do?

Identity Service Integration

  • Validate stand alone Cynergy with Identity
  • Roll out validated build and test
  • Deal with related OI (Data conversion etc)

Data Conversion

  • Complete rules for converting balances
    • Endowment underway
    • Plant account next
  • Validation of these rules for converting balances
  • Complete mappings and rules for other required chart attributes
    • Account, object code etc
  • Validation of these rules for other required chart attributes
  • Deal with any user provisioning
  • Rules for other charts (post PPI-1 launch)
  • Plan for future customizations

Data Mapping

  • Define end-user need
  • Fit gap against existing spreadsheets and audit tables
  • Do something, deliver something, operationalize

Environment(s)

  • Cynergy (stand alone) latest build deployment
  • Data conversion automation
  • Data Movement
    • Snapshot after data conversion, after batch, move to PPI-1 and ID&R staging
    • Automation of this snapshot
    • Validation process
  • Build and deploy DCP
  • Roll back process
    • Dev (done?), prove, practice

Batch Processing

  • Run two batches (Nominal Close, Beginning Balance Fund)
  • Determine if they'll be run via GUI or automate using comment line
  • Who is going to run it?
    • Add in automated script in the data conversion?
  • Validation
    • Logs and reports generated- interpreting them
    • Define success critetia

QA

  • For all functional processes, define success criteria, ID stakeholders
  • For all technical processes, define success criteria, ID stakeholders
  • Define use cases that will prove success criteria
  • QA tools (JIRA, test management, environment)
  • Identify and create test cases
  • Load testing - whether it is required

User Training

  • Identify users
  • Define use cases
  • Determine training requirements
  • Develop required material
  • Execute

ID&R and reporting

  • Define requirements
  • Modeling
  • ETL
  • Dashboard development
  • Validation
  • Training
  • Rollout
  • Support/ Maintenance
  • Feedback process

Feedback

  • Process for end user service
  • KFS and OBIEE
  • Tools (JIRA, special mailbox)
  • Issue management and customer service plan

Action Items

Action Required

Responsibility

Target Date

Acceptance criteria for PPI-1 functionality

Dave, Tony, Rina

5/17

Specific list of required chart attributes that must be validated for PPI by the date of rollout

Steve, Dave

5/13

Define end user data mapping requirements

Rina, Dave

5/13
Draft done (05/11),
to be updated based on user testing and reports

Review notes from refresh process (ie, the repeatable process we'll follow each time we update the balances) meetings.

All attendees

5/11
Links provided for review (05/10)

Publish FY10 accounting calendar with respect to our conversion process
DFA FY10 Published Calendar

Dave

5/11
Done (05/11)

Identify which ADW balances to pull and when

Dave, Steve, Rayna, Rina

5/17

Define (formally) service levels for PPI-1 support plan

Dave

5/10
Done (05/11)

Production support Plan

Open

 

Attendees to work on own milestones and deliverables based on review of these meeting notes

All attendees

5/11?

Schedule and Milestones

Date

Milestone

Notes

5/10/2010

Today

 

Week 1
5/17/2010

Data conversion mapping rules complete, including chart attributes and balances

 

Week 2
5/19/2010

Balance tables populated according to rules
DCP environment delivered and validated
Start functionally validating batch processes (use prior fiscal year data)

 

Week 3
5/24/2010

 

 

Week 4
6/01/2010

 PPI-1 Functionally validated
Some functional testing can begin

Major Milestone

Week 5
6/08/2010

 

 

6/01-6/15

Slush

 

Week 6
6/15/2010

Data Mapping freeze

 

6/15-6/25

Functional validation (QA and UAT period)

 

Week 7
6/22/2010

Validated conversion for 7/01/2010 release

 

6/25/2010

UAT Completed, Real freeze

 

6/25-7/1

Stasis period

 

Week 8
7/01/2010

PPI-1 Launch Date (beginning balances not available)

Major Milestone

7/28/2010

Functional FY10 Close, creation of FY11 Beginning Balances

 

7/30/2010

 

 


Open Issues (responsible persons)

  • Data conversion and user provisioning (Sarah, Steve, Aaron)
    • one data conversion process
    • convert all as we do for current environment and remove roles after
  • Data Mapping for end user requirements (Rina, Dave)
  • Load test for PPI-1? (Tony)
  • Sort out issues for data mapping freeze 6/15 (Steve)
  • Define ID&R milestones (Dave, Rayna, Butch)

Parking Lot

None