Time and labor estimates

Start-to-finish time (taking into account availability): 1.5 weeks (start 8/5, Mon?)

Est. labor: ~20 hours, including both Lulu's and Michael's time.

Work description

Effort
(usually hours)
Lulu, unless otherwise indicated

Elapse time
(usually days or weeks)

Test 3 HD’s stripe 0, S/W Raid

Lulu: 4 hours
Michael: 1 hour

.25 wk

Buy TB HD – 3 or 4 TB WD Black

Lulu: 2 hours
Michael: 2 hours

.5 wk

Install, configure

Lulu: 8 hours
Michael: 2 hours

.25 wk

Plan

See above work descriptions.

Use node 3 or 4.

Risks

And possible ways to address them.

Any?