You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 16 Next »

CIT STANDARD OPERATING PROCEDURE

Communication Unplanned Outages

Procedure Number: SOP 2010-000

Related Processes and Procedures:

DRP 20yy-000  Disaster Recovery Procedure Template
(None at this time, didn't know if we'd need to link this to a DR procedure later on).

Revision History

Date

Author

Version

Description

3/9/2010

ajl44

0.0

New Document

 

 

 

 

 

 

0.9

Final Draft

 

 

1.0

Approved Document

 

 

 

 

BACKGROUND AND PURPOSE

CIT Hosting Service customers need timely information regarding unplanned outages. In addition, responsible CIT departments must be notified. Status updates must be provided until outages are resolved.

SERVICES

CIT Hosting Services

Included Service

Service Owner

Service Manager

Service Dependencies

CommonSpot

Donna Taber

Nathan Reimer

 

ColdFustion

Donna Taber

Nathan Reimer

 

LAMP

Donna Taber

Nathan Reimer

 

Static

Donna Taber

Nathan Reimer

 

Fedora

Donna Taber

Richard Marisa

 

uPortal

Donna Taber

Jon Atherton

 

SCOPE

In Scope:

  • Details the steps necessary to communicate outages to CIT Hosting customers.
  • Identifies the roles and responsibilities of CIT staff, regardless of reporting structure, necessary to communicate outages to CIT Hosting customers.

Out of Scope:

  • Does not identify methods, steps or resources needed to resolve the outage issue.

CARD (Contingencies, Assumptions, Requirements, Dependencies)

(Indicate contingencies, assumptions, requirements and dependencies not indicated elsewhere which are required for execution of this procedure.)

Any relevant Contingencies, Assumptions, Requirements or Dependencies should be included.

  • Contingencies describe "what if" scenarios and how to accommodate them.
  • Assumptions are things which are presumed to be valid or true. Many assumptions will have a risk related to them.
  • Requirements are items which are necessary in order to successfully execute this procedure.
  • Dependencies are related items which depend on this procedure. Alternatively, the converse may also be relevant.

(If this section is not required, indicate "Not Applicable" rather than removing this section from the document).

TASK DESCRIPTION

Provide a description of the individual tasks which constitute the SOP.

Task Number

Task Description

Responsible Party

1.            

Report all incidents to the NOC every time (call 255-9900). Don't assume someone else will be doing this!

Service Owner/Service Support Team

1.1

Update the NOC regularly to keep them in the loop. Tier one services require hourly updates.

Service Owner/Service Support Team

1.2      

Once resolved, provide outcome information to the NOC; include what happened and how you fixed it.

Service Owner/Service Support Team

2.            

Engage the service owner/service support team (if not already confirmed to be involved).

NOC

2.1            

Provide internal communications support.

NOC

2.2            

Update the CIT status page.

NOC

2.3            

Involve Communication & Outreach when necessary.

NOC

3            

Click on thumbnail for full image.

Various

PEOPLE

Title

Role

Service Owner

Point of escalation for major incidents.

Service Owner

Developing and executing the Service's outage communications plan. Executing the outage communications plan may be delegated.

Service Manager

Responsible for internal planned outage communications. May be responsible for external planned outage communications.

Service Support Team

Provide timely outage status updates

APPENDICES and ATTACHMENTS follow the approval block.

Approvals

Name

Function

Comments

Signature

Date

 

Director

 

 

 

 

Service Owner

 

 

 

 

Service Manager

 

 

 

Appendix A: References

Communicating Unplanned Outages

Appendix B: Second Appendix

Include any material for Appendix B as referenced in the main document.

Add additional appendices, as required.

(If this Appendix is not required, remove this appendix from the document).

 

(Add any attachments that may have been too large to include in the main text portion of this document.  Label as Attachment 1, Attachment 2, etc.)
 

  • No labels