Honduras Interns Progress Report
Date: 9/20/07

Location: Ojojona

Work Completed This Week

Progress in Problem Solving

Capacitation of plant operators

*Alexis is in charge of the plant this week. We gave him some training Monday and he seems to pick up on things more quickly than Mario and Juan. When we got back on Friday we were very happy to note that Alexis had been taking good care of the plant. When we got here it rained a lot that morning and the water was dirty but he had already upped the dose and was cleaning the distribution tank since it was at about 100 and made a new barrile of sulfate. He made changes during the week to ensure the plant was flocculating and kept a very neat and precise record of everything.

Moroceli

Questions, work for Cornell Team

Plant Improvement Ideas

Plans for the Future

New Laminas

Sedimentation tank

Try experiments with the sedimentation tanks:
First one is to see if we can take one of them offline and still produce clean water.
Second is that we need to cut the entrance pipes to the sedimentation chambers so that the pipe that goes to the floor has holes that are as large as possible.
Third is to completely remove the entrance pipes so that all the flow enters at the beginning of the tank
Get materials to take the water from the overflow chamber away from the plant.
Look into the possibility of buying Ferric chloride, the supplier of aluminum sulfate doesn´t appear to have it on their website.

Trips: