Overview

There are 5 #sedimentation tanks in the Marcala plant, each with two sub-sections that drain through their respective effluent launder pipes. Eight of the 10 sub-tanks have the effluent launders installed and are attached to what will be the plant leveling tank. Currently we are working on including the design of the additional 2 sub-tanks. The number and size of the orifices in each effluent launder must be designed to account to reduce the difference in flow between the longest and shortest flow paths from the sedimentation tanks to the plant leveling tank.

The design program can be seen in Marcala Launder orifice design MathCAD File

Design Constraints

Marcala Tank Dimensions