Go-Live Cutover Plan
| Date |
Stop editing vendor records (addresses, etc.) and load them into FOLIO | June 1 |
Stop adding to Voyager authority queue | June 1 |
Pause BorrowDirect & Inter-Library Loan | June 7 |
Pause new acquisitions | June 14 |
Stop adding and updating bibliographic and holdings; including peripheral tasks that change bibliographic and holdings | June 14 |
Stop authority control | June 14 |
Requesting stops in Voyager | June 16 |
LTS stop processing invoices | June 17 |
Stop adding and updating item data | June 21 |
Close books in Voyager | June 21 |
Pause circulation | June 21 |
Re-open books / go-live in FOLIO • Resume all ordering/receiving/serials check-in activities as soon as we have the go ahead from Library Finance and Budget and FOLIO Implementation Team | July 1 |