  1. Flip Book for Rare Manuscripts
    1. Project Lead: Gabriel
    2. Project Status
    3. Project Timeline: 
  2. Stone Classroom AV upgrade to include videoconferencing
    1. Project Lead: Matt
    2. Project Status
      1. Estimates from vendor obtained, ~$21,000
      2. Project send to CIT-Integrated AV for second quote, which costs $2,500. Has not yet been approved
      3. Ezra Delaney is looking for funding from CALS first, then if denied for CUL funding
    3. Timeline: Winter Break 2017 installation (tentative)
  3. Data Dashboard
    1. Project Lead: Nick
    2. Project Status
      1. Initial proof of concept built during Feb 2016 Tech Innovation Week
      2. Demoed to MaLT during June 2016 meeting
      3. Project is documented on GitHub
    3. Project Timeline: Tentative (very) outlined on GitHub